Crossroads 2000 Project Tables
Crossroads 2000 is the name Indiana governor Frank O'Bannon gave to his
four year highway construction plan. In the main, this plan breaks no new
ground. Virtually every project is one that has been in the works for years.
Indeed, it would seem suspicous if this was not the case due to the large
lead time needed to bring major projects to a point where they can be
constructed.
But there are a few major expenditures that are going towards projects that
had not been previously funded. These projects are:
- The Hoosier Heartland Corridor between Lafayette and Fort Wayne
- The I-80/I-94 interchange at Cline Ave (SR 912)
- The Bloomington to Evansville freeway (design work only)
The remainder of the projects had been programmed for some time.
The tables below list all major projects by county. Note that all dollar
amounts are in thousands. The preservation amounts are for the entire four
years of the Crossroads 2000 plan.
Adams County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Added travel lanes on US 27 from SR 124 to US 27/US 33 at Decatur
|
| 9000
|
|
| 20000
|
| Preservation
| 2056
|
| Total
| 31056
|
Allen County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Added travel lanes on US 33 from US 30 to Cook Road
|
|
|
|
| 6000
|
| Interchange modification on I-69 at US24 southwest of Fort Wayne
|
| 5096
|
|
|
|
| Added travel lanes on I-69 at the interchange with SR 3
|
|
| 4285
|
|
|
| Preservation
| 11019
|
| Total
| 26400
|
Bartholomew County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Added travel lanes on SR 46 from I-65 to Columbus
| 6500
| 7957
|
|
|
|
| Road construction on SR 46 from SR 9 to 1 mile east of SR 9
|
|
|
|
| 6000
|
| Road construction on SR 46 from SR 7 to US 31
|
|
| 1400
|
|
|
| Preservation
| 11779
|
| Total
| 33636
|
Benton County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 6458
|
| Total
| 6458
|
Blackford County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 650
|
| Total
| 650
|
Boone County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Added travel lanes on SR 32 at I-65 interchange
|
|
|
|
| 1000
|
| New Road Construction on SR 334 in Zionsville
|
|
|
|
| 1502
|
| Added Travel Lanes on US 421 from Marion/Hamilton County line to SR 334
|
|
|
| 13840
|
|
| Preservation
| 11060
|
| Total
| 27402
|
Brown County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 2495
|
| Total
| 2495
|
Carroll County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 5937
|
| Total
| 5937
|
Cass County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| New road construction on US 24, Hoosier Heartland from Logansport to Peru
| 25150
| 7500
|
|
|
|
| Preservation
| 6372
|
| Total
| 39022
|
Clark County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Added travel lanes on I-65 from the Ohio River to SR 311
|
| 4935
|
| 37790
| 36953
|
| Preservation
| 9290
|
| Total
| 88968
|
Clay County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 5987
|
| Total
| 5987
|
Clinton County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| New road construction on SR 28 from I-56 to just west of SR 39 at Frankfort
|
|
|
|
| 10000
|
| New road construction on US 421 at Frankfort
|
|
|
|
| 2468
|
| Preservation
| 2281
|
| Total
| 14749
|
Crawford County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| New road construction on SR 145 from I-64 to SR 64
|
|
|
|
| 35321
|
| Preservation
| 6254
|
| Total
| 41575
|
Daviess County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 6053
|
| Total
| 6053
|
Dearborn County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| New road construction on SR 48 from SR 148 to US 50
|
| 1600
|
|
|
|
| Preservation
| 533
|
| Total
| 2133
|
Decatur County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 25
|
| Total
| 25
|
Dekalb County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 27812
|
| Total
| 27812
|
Delaware County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Road construction on SR 67 from I-69 to the Muncie Bypass
| 14009
|
|
|
|
|
| Preservation
| 8799
|
| Total
| 22808
|
Dubois County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| New road construction on US 231, Jasper/Huntingburg Bypass
|
|
|
|
| 78000
|
| Preservation
| 7689
|
| Total
| 85689
|
Elkhart County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Road construction on SR 15 from US 20 to 2 miles north of US 20
|
|
|
|
| 4825
|
| Added travel lanes on SR 19 in Elkhart from US20 to US 33
|
|
|
|
| 20000
|
| Added travel lanes on US 33 in Goshen, from CR 40 to south jct of SR 15
|
|
|
|
| 3250
|
| Added travel lanes on US 33 in Goshen, from Chicago Ave to Indiana Ave
|
|
|
|
| 1100
|
| Preservation
| 4003
|
| Total
| 33178
|
Fayette County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Added travel lanes on SR 1 at Connersville
|
| 3250
|
|
|
|
| Preservation
| 495
|
| Total
| 3745
|
Floyd County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 23876
|
| Total
| 23876
|
Fountain County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 13430
|
| Total
| 13430
|
Franklin County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Added travel lanes on SR 46, from just west of SR 229 to Winding Way
|
| 5904
|
|
|
|
| Preservation
| 8538
|
| Total
| 14442
|
Fulton County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 4073
|
| Total
| 4073
|
Gibson County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| New road construction on Southwest Indiana Highway Corridor Evansville to Bloomington, from Evansville to Petersburg
|
|
| 15000
|
|
|
| Preservation
| 8149
|
| Total
| 23149
|
Grant County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Added travel lanes on SR 9 at Marion
|
| 8433
|
|
|
|
| Preservation
| 3987
|
| Total
| 12420
|
Greene County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 3584
|
| Total
| 3584
|
Hamilton County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Added travel lanes on SR 37 from 2 miles norht of SR 32 to 3.5 miles north of SR 32
|
|
|
|
| 3000
|
| New road construction on SR 38 at Noblesville
|
| 1700
|
|
|
|
| Bridge Rehabilitation on I-69 at 116th Street
|
| 3900
|
|
|
|
| Interchange modification on I-69 at SR 238 interchange
|
|
|
|
| 350
|
| Added travel lanes on SR 431 at Carmel from 96th Street to US 31
|
|
|
|
| 390
|
| Preservation
| 8806
|
| Total
| 18146
|
Hancock County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 17084
|
| Total
| 17084
|
Harrison County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Road construction on SR 135 from US 150 at Palmyra to SR 60 at Salem
|
|
|
|
| 14860
|
| Preservation
| 4347
|
| Total
| 19207
|
Hendricks County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Added travel lanes on US 40 from SR 267 to the Hendricks/Marion County lin
|
| 12200
|
| 12142
|
|
| Interchange modification on I-70 at SR 267
| 4488
|
|
|
|
|
| New interchange construction on I-74 near the Marion/Hendricks County line
|
|
|
|
| 3500
|
| Preservation
| 25569
|
| Total
| 57899
|
Henry County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Road construction on SR 103 from 3 miles south of SR 38 to SR 38
|
|
|
|
| 1400
|
| Preservation
| 6996
|
| Total
| 8396
|
Howard County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Road construction on SR 22 at Kokomo
|
|
|
|
| 1160
|
| Preservation
| 713
|
| Total
| 1873
|
Huntington County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| New road construction on US 24, Hoosier Heartland from Wabash to Huntington
| 4000
| 24950
|
|
|
|
| Preservation
| 3368
|
| Total
| 32318
|
Jackson County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Road Construction on US 50 from Brownstown to 1.3 miles west of US 50/SR11 in Seymour
| 5700
|
| 4305
|
|
|
| Preservation
| 30793
|
| Total
| 40798
|
Jasper County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 4514
|
| Total
| 4514
|
Jay County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 8588
|
| Total
| 8588
|
Jefferson County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 7891
|
| Total
| 7891
|
Jennings County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 4953
|
| Total
| 4953
|
Johnson County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 3123
|
| Total
| 3123
|
Knox County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Road construction on SR 67 from US 41 to Bicknell
|
|
|
| 12973
|
|
| Preservation
| 12818
|
| Total
| 25791
|
Kosciusko County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 1049
|
| Total
| 1049
|
LaGrange County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Road construction on US 20 from SR 5 to 3 miles east of SR 5
|
|
|
|
| 5310
|
| Preservation
| 1401
|
| Total
| 6711
|
Lake County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Added travel lanes on US 6 from SR 51 to SR 149
|
|
|
|
| 13900
|
| Added travel lanes on US30 at the Merrillville interchange
|
| 1118
|
|
|
|
| Added travel lanes on US 41 from I-80 to US 12/20
|
| 2530
|
|
|
|
| Added travel lanes on US 51 from Hobart Road to US 20
|
| 4300
|
|
|
|
| Added travel lanes on SR 53 from 1 mile north of US 30 to just south of 61st Ave
|
|
|
|
| 1300
|
| Added travel lanes on SR 55 from 93rd Ave to US 30
|
| 6100
|
|
|
|
| Added travel lanes on I-65 from US 231 to US 30
|
|
|
|
| 62662
|
| Interchange modification on I-65 at 61 Street in Merrillville
|
|
| 10144
|
|
|
| Freeway Management System on I-80
|
| 2000
| 7000
|
|
|
| Interchange modification on I-80 at Grant Street
|
| 2854
|
|
|
|
| Interchange modification on I-80 at Burr Street
| 11730
|
|
|
|
|
| Interchange modification on I-80 at SR 912
| 22693
| 15287
| 11355
| 19360
|
|
| Preservation
| 107742
|
| Total
| 302075
|
LaPorte County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Added travel lanes on US 35, at the jct with SR 39
|
|
|
|
| 7600
|
| Preservation
| 14247
|
| Total
| 21847
|
Lawrence County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Added travel lanes on SR 37, from SR 60 at Mitchell to 1.4 miles north of west jct with SR 60
|
| 15000
|
|
|
|
| Road construction on SR 50 at Bedford
|
|
| 7300
|
| 10637
|
| Preservation
| 8805
|
| Total
| 41742
|
Madison County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Road construction on SR 9 from SR 32 to SR 128
|
|
| 7164
|
|
|
| Road constructon on SR 13 at Elwood
|
|
| 6700
|
|
|
| Preservation
| 6941
|
| Total
| 20805
|
Marion County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Added travel lanes on US 31 from Mills Ave to Southern Ave
|
|
|
|
| 8460
|
| Added travel lanes on US 31 from 86th St. to 96th St.
|
|
|
|
| 6000
|
| Added travel lanes on US 36 from I-465 to 6 miles NE of I-465
|
|
|
|
| 37000
|
| Added travel lanes on US 40 from Franklin Road to Buck Creek
|
|
|
|
| 13400
|
| Added travel lanes on US 52 from I-465 to Post Road
|
|
|
| 4970
|
|
| New interchange construction on I-65 at the Marion/Johnson County line
| 8930
|
|
|
|
|
| Interchange modification on I-70 at Post Road
| 22377
|
|
|
|
|
| Interchange modifcation on I-465, Shadeland Ave to Fall Creek Bridge
|
|
|
|
| 44993
|
| Preservation
| 175366
|
| Total
| 321496
|
Marshall County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Added travel lanes on SR 17 at Plymouth
|
|
|
|
| 8000
|
| Preservation
| 14205
|
| Total
| 22205
|
Martin County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 2820
|
| Total
| 2820
|
Miami County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| New road construction on US 24, Hoosier Heartland from Logansport to Peru
| 25150
| 7500
|
|
|
|
| Preservation
| 1740
|
| Total
| 34390
|
Monroe County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Added travel lanes on SR 46, Ellettsville to Bloomington
|
|
| 45440
| 7380
| 2238
|
| Added travel lanes on SR 48, from 2.5 miles west of SR 37 to 0.5 miles west of SR 37
|
|
|
|
| 9200
|
| Road construction on SR 446 at Bloomington from Allen's Creek Road to Chapel Hill Road
|
|
|
|
| 950
|
| Preservation
| 13061
|
| Total
| 78269
|
Montgomery County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Added travel lanes on US 231 at Crawfordsville
|
|
|
|
| 13000
|
| Preservation
| 14030
|
| Total
| 27030
|
Morgan County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 14707
|
| Total
| 14707
|
Newton County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 3370
|
| Total
| 3370
|
Noble County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Added travel lanes on US 6 at Kendallville
|
|
|
| 2500
|
|
| Preservation
| 2183
|
| Total
| 4683
|
Ohio County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 1971
|
| Total
| 1971
|
Orange County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Road construction on SR 145 from French Lick to Mitchell
|
|
|
|
| 72000
|
| Preservation
| 9394
|
| Total
| 81394
|
Owen County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 3471
|
| Total
| 3471
|
Parke County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Road construction on US 41 to 0.5 mile south of US 36 to 2 miles north of US 36
|
|
|
|
| 4757
|
| Road construction on US 41, 2.5 miles north of SR 163
|
|
|
|
| 4000
|
| Preservation
| 7291
|
| Total
| 16048
|
Perry County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Road construction on SR 37 at Tell City
|
| 1748
|
|
|
|
| Road construction on SR 37 from Lincoln Trail Bridge up SR 237 to existing SR 37
|
|
|
| 27000
|
|
| New road construction on SR 145 from I-64 to SR 64
|
|
|
|
| 35321
|
| Preservation
| 6313
|
| Total
| 70382
|
Pike County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| New road construction on Southwest Indiana Highway Corridor Evansville to Bloomington, from Evansville to Petersburg
|
|
| 15000
|
|
|
| Preservation
| 4743
|
| Total
| 19743
|
Porter County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| New interchange on I-94 at the Porter/LaPorte County line
|
|
|
|
| 2142
|
| Preservation
| 26916
|
| Total
| 29058
|
Posey County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Road construction on SR 69 from Mt Vernon Bypass to I-64
| 12350
|
| 26100
|
|
|
| Preservation
| 31309
|
| Total
| 69759
|
Pulaski County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 3105
|
| Total
| 3105
|
Putnam County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Road construction on US 231 in Cloverdale, from 2 miles south of I-70 to 1 mile south of I-70
|
|
|
|
| 2323
|
| New road construction on SR 240, from 3 miles east of US 231 to 4 miles east of US 231
|
|
|
|
| 1008
|
| Preservation
| 10668
|
| Total
| 13999
|
Randolph County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 2508
|
| Total
| 2508
|
Ripley County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 715
|
| Total
| 715
|
Rush County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 3611
|
| Total
| 3611
|
Saint Joseph County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Added travel lanes on SR 23, from the Toll Road to 5.6 miles south of the Indiana/Michigan state line
| 3010
|
|
|
|
|
| Added travel lanes on SR 23 in South Bend & Mishawaka, from Eddy Street to Twychkenham Road
|
|
|
|
| 1907
|
| Added travel lanes on US 33, from Mishawaka to the St. Joseph/Elkhart County line
|
|
|
|
| 1324
|
| Preservation
| 16222
|
| Total
| 22463
|
Scott County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 4548
|
| Total
| 4548
|
Shelby County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 14707
|
| Total
| 14707
|
Spencer County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Bridge construction on US 231, near Rockport (Indiana share)
|
|
|
|
| 55637
|
| New road construction on US 231 from the Ohio River to I-64
|
|
|
|
| 93495
|
| Preservation
| 5500
|
| Total
| 154632
|
Starke County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Road construction on US 35, from SR 8 to Knox
|
|
|
| 5050
|
|
| Preservation
| 11214
|
| Total
| 16264
|
Steuben County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 23642
|
| Total
| 23642
|
Sullivan County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 8354
|
| Total
| 8354
|
Switzerland County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Road construction on SR 129 from SR 56 to SR 250
|
|
|
|
| 15000
|
| Preservation
| 4515
|
| Total
| 19515
|
Tippecanoe County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Added travel lanes on SR 26, from I-65 to 1.5 miles east of I-65
|
|
|
|
| 6200
|
| New road construction on US 231, from SR 25 to the US 231/SR 43 interchange
| 9617
| 11698
|
|
|
|
| Preservation
| 10813
|
| Total
| 38328
|
Tipton County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 1582
|
| Total
| 1582
|
Union County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 3657
|
| Total
| 3657
|
Vanderburgh County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Interchange modification on SR 66 in Evansville at Green River Road
|
|
|
| 9117
|
|
| Added travel lanes on SR 66 from Evansville (Green River Road) to I-164
|
| 6000
|
|
|
|
| Road construction on SR 66 in Evansville, from St. Joseph Ave to US 41
|
|
|
|
| 16689
|
| Preservation
| 30370
|
| Total
| 62176
|
Vermillion County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 15059
|
| Total
| 15059
|
Vigo County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Weigh station construction on I-70 ath the Illinois State Line
|
|
| 5886
|
|
|
| New road construction on SR 641, from US 41/150 south of Terre Haute to SR 46 east of Terre Haute
|
|
|
|
| 45500
|
| Preservation
| 10619
|
| Total
| 62005
|
Wabash County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| New road construction to US 24, Hoosier Heartland, from Wabash to Huntington
| 4000
| 24950
|
|
|
|
| Preservation
| 5303
|
| Total
| 34253
|
Warren County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Road construction on SR 26, from US 41 to SR 55
|
| 4500
|
|
|
|
| Preservation
| 3281
|
| Total
| 7781
|
Warrick County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Added travel lanes on SR 62, from I-164 to Boonville
|
|
|
|
| 47050
|
| Added travel lanes on SR 66 from I-164 to Yankeetown Road
|
|
| 12500
|
| 28335
|
| Road construction on SR 662 in Newburgh
|
|
|
|
| 3143
|
| Preservation
| 3762
|
| Total
| 94790
|
Washington County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Road construction on SR 13 from US 150 at Palmyra to SR 60 at Salem
|
|
|
|
| 14861
|
| Preservation
| 5287
|
| Total
| 20148
|
Wayne County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Road construction on SR 1 from Connersville to Milton
|
|
|
|
| 4085
|
| Preservation
| 38556
|
| Total
| 42641
|
Wells County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 1573
|
| Total
| 1573
|
White County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 5257
|
| Total
| 5257
|
Whitley County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 1308
|
| Total
| 1308
|
Various County
| Description
| 1998
| 1999
| 2000
| 2001
| 2002+
|
| Preservation
| 600000
|
| Total
| 600000
|