West I-70 Interchanges and Widening
INDOT now has its own web page
devoted to this project, so I will allow them to speak for themselves
on it. My page will remain here to provide historical information on
the development of this project.
There is a seven mile stretch of I-70 west between I-465 and SR 267 which
is six lanes, but has no interchanges. This was identified as a deficiency
long ago. Various studies looked at this, but nothing was done. This changed
recently due to a number of factors:
- United Airlines built a large maintenance facility at the Indianapolis
airport. Currently the only access to that facility is off
Washington St., which cannot handle the projected traffic load. This base
was originally supposed to employ 7,200 people, but has fallen far short
of its goals to date. Still, it is a major employer.
- The Indianapolis Airport Authority is relocating its
passenger terminal (which cannot be expanded in its current location) to a
new midfield location on the west side of the airport. This will require
a new interchange on I-70.
- FedEx has its second largest package sorting hub at the Indianapolis
airport. The current facility is landlocked with no room for expansion.
Relocation of the freeway to the south would enable FedEx to grow and add in
excess of 1,000 jobs.
- There is no north-south through route linking I-70 with I-74 and I-65
between I-465 and SR 267. This was projected to cause substantial traffic
problems because of massive residential growth in eastern Hendricks County.
Thus the Hendricks County Commissioners developed a plan to build a new four
lane limited access arterial to link I-70 and I-74, roughly following the route
of CR 1000E, CR 1050E, and Six Points Rd. This road would need to connect
to both I-70 and I-74.
- Large industrial parks are under development in Plainfield. There is a
large amount of vacant land between Plainfield and the airport that cannot
be developed for residential due to noise problems, so the town wants to
use it for light industrial purposes. However, much of this land is
located too far from an interstate interchange to make it attractive to
developers.
- This section of I-70 is in need of rehabilitation. Substantial funds will
need to be devoted to this route in the near future whether or not it is
improved.
INDOT hired American Consulting Engineers to study this roadway. They
proposed a combination of capacity expansion projects that would satisfy all
of these needs. This project will cost approximately $150 million (including
some costs to upgrade Six Points Rd. but excluding the cost to upgrade the
I-70 West/I-465 interchange). Project elements include:
- Widening and realigning Six Points Rd. This route will be widened to
four lanes north of I-70 with a continuous two way left turn lane (TWLTL)
median. Just north of I-70, the road will curve eastward to cross I-70
at a 90 degree angle and continue southeasterly to a new terminus at
Kentucky Ave. This section will be six lanes with a TWLTL median.
- New interchange construction at Six Points Rd. This will be an enhanced
cloverleaf with flyover ramps from outbound I-70 to southbound Six Points
and from southbound Six Points to inbound I-70. There will also be a C/D
system interconnected with the a new Airport interchange.
- New Airport spur off I-70 to serve a new midfield terminal. This will
include dual lane ramps connecting the airport with inbound I-70. Braided
ramps will connect with the adjacent Six Points Rd. interchange.
- Widening I-70 to four lanes each way between Six Points Rd. and I-465
with a new barrier median. A section of the roadway will also be relocated
to the south and depressed in order to allow two new aircraft taxiways to
be constructed over I-70. (A land swap with a developer preserved land
south of I-70 needed for a third runway).
- Removal of existing overpasses at old Six Points Rd., Hanna Ave., and
Bridgeport Rd.
- Improvement of the I-70 West/I-465 interchange to create a dual lane
ramp from I-465 south to outbound I-70. And replacing the loop ramp from
inbound I-70 to northbound I-465 with a new flyover ramp.
There are substantial environmental impacts from this project. A portion of
White Lick Creek will need to be relocated. This is a habitat for the
endangered Indiana bat (or some other endangered species. I do not remember
sure). So there will need to be extensive environmental mitigation. To
date I am not aware of any real opposition to this project from environmental
groups. This is a bit surprising given the amount of impact this project has,
plus the fact that it could be considered a classic sprawl inducer. (Indeed,
one of the explicit goals of the project is to open up vacant land on the
urban fringes to development).
A more serious barrier is funding. Here is a cost breakdown for the
various portions of the project:
| Description
| Cost
|
| Six Points Rd. (north of I-70 to Washington St.)
| 7,900,000
|
| Six Points Rd. (south of I-70 to Kentucky Ave.)
| 7,000,000
|
| Six Points Rd. interchange
| 62,000,000
|
| Airport interchange
| 39,000,000
|
| I-70 widening/relocation
| 33,000,000
|
| I-70 West/I-465 interchange
| N/A
|
While there is funding included for
this project in the long range plan, it is all "special" funding, meaning it
is not budgeted out of normally available funds. Some money was authorized
as part of the TEA-21 bill, but I don't believe anything has actually
been appropriated. INDOT has $10 million budgeted to rehab I-70, and I
hear they reached a deal with the City of Indianapolis to pay half of
the cost of the relocation of I-70 to accomodate a FedEx expansion. (The
deal was actually a no cash transaction. Indianapolis simply agreed to
take over the short section of Shadeland Ave. that was signed as SR 100
and the state credited them with $10 million towards the project).
Hendricks County has been frustrated in its efforts to get federal
funding for a section of the North-South Corridor futher north that it
is trying to build.
INDOT recently issued an RFP (350K PDF Format) for
a consultant to being work on this project. This project had previously
been bogged down for some unknown reason, but with the Airport Authority
voting to proceed with a new midfield terminal to open in 2007, INDOT
has put this project on the fast track. Contracts are to be let in mid-2003
with an opening of the entire segment by December 2004. This may include
only a scaled down version of the Six Points Rd. interchange, however.
The estimated cost is $125,000,000. Subsequent to this RFP, I spoke
with an INDOT employee who confirmed that this project is moving along.
Last Update: January 2003
Copyright © 1998-2003 Aaron M. Renn
(arenn@urbanophile.com)
All Rights Reserved
Back to my Indianapolis major investments page or up
to my homepage.
Just Say No to Frames, Ads, and Animated GIF's